Branscome was hired by Ryan Construction to complete the Pier IX Terminal Cement Stabilization project at the Pier IX Coal Terminal in March of 2014. Branscome utilized two crews to spread approximately 800 tons of cement, perform manipulation of cement into the existing subgrade, and stabilize 18,000 SY of area near the new terminal expansion. The job was completed on schedule, allowing the new coal operation to begin on time.